“The use of SymTerra on the Liverpool St Project allowed MTR to obtain live updates from site on over 500 planned activities during our critical 10-day Easter blockade.
This allowed the project team to update the hour-by-hour programme in real-time, identify any change to the critical path and effectively re-sequence works or re-allocate resources to ensure completion on time.
These updates also allowed us to obtain comprehensive visibility over what was happening on site and enabled us to confidently report back to stakeholders on progress.
— Matthew Stimson (MTREL Project Manager).